EXECUTIVE ENIGINEER ,NH , DHENKANAL (Physical & Financial Progress of NH (Original) &P/R works of N.H.Division, Dhenkanal for the month ending May 2010 (Dhenkanal District) (Rs.in lakhs) |
| Physical & Financial Progress of NH (Original) &P/R works of N.H.Division, Dhenkanal for the month ending May 2010 (Dhenkanal District) (Rs.in lakhs) | ||||||||||||||
| Sl.No | Name of work | As per sanctioned estimate | Agt. No | Name of Agency | Agt. Value | Date of commencement | Stipulated date of completion | Actual date of completion | Expr. upto 31.3.09 | Expr. upto 31.3.10 | Expr. upto 31.5.10 | Physical progress of work | Remarks | |
| Km | Amount | |||||||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 |
| NH.42 (Original works) | ||||||||||||||
| 1 | Strengthening of NH.42 from 56/0 to 66/0Km for the year 2008-09. (Job No 042-ORS-2008-09-398) | 10.000 | 713.04 | SBD-01 of 2008-09 | M/s.Nanda Const. | 636.98 | 15.1.09 | 14.9.09 | 31.1.2010 | 216.84 | 619.66 | 0.00 | Work Completed | Final bill is in process at Sub-Division level. |
| 2 | Strengthening of NH.42 from 73/0 to 87/570Km (except 84/500 to 85/500Km & 87/0 to 87/570Km) for the year 2008-09. (Job No 042-ORS-2008-09-399) | 11.000 | 818.76 | SBD -03 of 2008-09 | Sri Durga Condev Pvt.Ltd | 731.67 | 2.2.09 | 1.10.09 | 30.3.2010 | 0.00 | 710.70 | 0.00 | Work Completed | Final bill is in process at Sub-Division level. |
| 3 | Strengthening of NH.42 from 89/540 to 99/00Km for the year 2008-09. (Job No 042-ORS-2008-09-396) | 9.480 | 596.70 | SBD-02 of 2008-09 | Samal Builders | 520.58 | 30.1.09 | 29.9.09 | 28.2.2010 | 32.70 | 524.97 | 0.00 | Work Completed | Final bill is in process at Sub-Division level. |
| NH.42 (IRQP works) | ||||||||||||||
| 1 | Improvement to Riding Quality to NH.42 from 31/0 to 33/0km & 34/0 to 36/0Km for the year 2008-09 (Job No 042-ORS-2008-09-439) | 4.000 | 206.42 | 02-P1 of 2009-10 | Om Maa Constn. | 161.89 | 23.6.09 | 22.9.09 | 22.12.2009 | 0.00 | 172.53 | 0.00 | Work completed | Final bill is in process at Sub-Division level. |
| 2 | Improvement to Riding Quality to NH.42 from 67/0 to 71/0Km for 2008-09 (Job No 042-ORS-2008-09-436) | 4.000 | 204.61 | No.01-P1 of 2009-10 | Sri Pradeepta Ch. Rath | 159.27 | 19.6.09 | 18.9.09 | 31.1.2010 | 0.00 | 162.60 | 0.00 | Work completed | Final bill is in process at Sub-Division level. |
| NH.42 (Deposit works) | ||||||||||||||
| 1 | Construction of ROB with approaches near canal crossing no. 88/112 from 87.65 to 88.75Km (87/0 to 89/950Km) of NH.42 | 2.950 | 4506.50 | SBD 01 of 2010-11 | M/s.ARSS Infrastructure Project Ltd. | 3592.15 | 5.4.2010 | 4.4.2012 | 0.00 | 0.00 | 0.00 | Excavation of foundation for abutment in Dhenkanal side and one pier is in progress | ||
| 2 | Realignment from 84/500 to 85/500 of NH.42 Bhusan Deposit | 1.000 | 289.79 | No.09/P-1 of 2009-10 | M/s.Nanda Const. | 227.47 | 1.2.2010 | 30.9.2010 | 0.00 | 0.00 | 0.00 | Utiliting shifting & trees cutting. Work is in pending. | ||
| NH.200 (P/R works) | ||||||||||||||
| 1 | P/R to stretches from 301/893 to 309/0Km & 319/0 to 332/0Km of NH.200 for the year 2009-10 (Job No.TA-200-ORS-2009-10-768) | 12.107 | 293.99 | No.04/P-1 of 2009-10 | Baji Behera | 265.21 | 18.12.09 | 17.4.2010 | 0.00 | 66.09 | 0.00 | 7.107Km PCSC & 5.00Km SDBC completed. | Bill amountig to Rs. 65.68 lakhs submitted to MosRT&H | |
| 2 | P/R to stretches from 309/0 to 319/0Km & 332/0 to 342/0Km of NH.200 for the year 2008-09 (Job No TA-200-ORS-2008-09-727) | 20.000 | 310.52 | No.03-P1 of 2008-09 | M/s.S.N. Sharma | 262.78 | 11.11.08 | 10.3.09 | 9.03.2009 | 147.91 | 278.12 | 0.00 | Work completed & final bill paid | |
| 3 | P/R to stretches from 342 to 352Km of NH.200 for the year 2009-10 (Job No.TA-200-ORS-2009-10-769) | 10.000 | 148.97 | No.11/P-1 of 2009-10 | Subhalaxmi Swain | 135.82 | 19.2.10 | 18.5.10 | 0.00 | 99.37 | 0.00 | Work completed. | Final bill is in process at Sub-Division level. | |
| Executive Engineer. N.H.Division, Dhenkanal | ||||||||||||||