PHYSICAL AND FINANCIAL ACHIEVEMENT UNDER "MOKUDIA" for the year 2009-10 
  DISTRICT:  DHENKANAL               Month: JAN-2010        
                           
      FINANCIAL             PHYSICAL        
Sl No BLOCK O.B as on 1.4.008 Funds released Total Expenditure    Target   No of work order issued   Status    of the  House  
          Spill 2009-10 Total   Completed  Plinth level Roof casted Construction not started Work order yet to be issued
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1 BHUBAN 20.40 12.60 33.00 16.34 68 36 104 76 22 26 19 9 28
2 GONDIA 38.65 22.40 61.05 26.40 122 64 186 92 3 62 12 15 94
3 ODAPADA 29.00 16.45 45.45 24.53 90 47 137 115 11 52 19 33 22
4 HINDOL 41.65 23.80 65.45 18.20 129 68 197 108 3 48 16 41 89
5 SADAR 31.20 18.55 49.75 11.26 101 53 154 102 7 26 12 57 52
6 K.NAGAR 26.20 15.40 41.60 14.56 85 44 129 91 8 32 13 38 38
7 KANKADAHAD 27.45 15.40 42.85 12.35 85 44 129 52 2 24 6 20 77
8 PARJANG 32.00 17.50 49.50 15.86 96 50 146 96 0 20 0 76 50
  TOTAL 246.55 142.10 388.65 139.50 776 406 1182 732 56 290 97 289 450