| PHYSICAL & FINANCIAL ACHIEVEMENT UNDER CONSTRUCTION OF AWC BUILDINGS UNDER WORLD BANK ASSISTED ICDS-III PROJECTS | ||||||||||||
| Month:- JAN-2010 | ||||||||||||
| Physical Progress | ||||||||||||
| Sl. No | Name of the Block | No.of AWC Sanctioned @ Rs.93750/- per unit | Amount Released | Expenditure Incurred | U.C.Submitted | Plinth Level | Lintel Level | Roof Level | Roof Casted | Completed | Not Started | Remarks |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 |
| 1 | Odapada | 60 | 56.25 | 56.25 | 56.25 | 4 | 0 | 7 | 17 | 32 | 0 | |
| 2 | Gondia | 28 | 26.25 | 26.25 | 26.25 | 0 | 0 | 1 | 25 | 2 | 0 | |
| 3 | Sadar | 123 | 115.31 | 112.44 | 112.44 | 1 | 7 | 21 | 73 | 21 | 0 | |
| 4 | Hindol | 100 | 93.75 | 91.00 | 91.00 | 7 | 12 | 18 | 9 | 52 | 2 | |
| Total | 311 | 291.56 | 285.94 | 285.94 | 12 | 19 | 47 | 124 | 107 | 2 | ||